A PHP Error was encountered

Severity: Warning

Message: get_headers(): This function may only be used against URLs

Filename: views/page_view.php

Line Number: 499

A PHP Error was encountered

Severity: Warning

Message: array_change_key_case() expects parameter 1 to be array, boolean given

Filename: views/page_view.php

Line Number: 499

Application of Project Management using CPM (Critical Path Method) and Pert (Project Evaluation and Review Technique) in the Nava House Bekasi Cluster Housing Development Project


Authors : Fajar Garninda; Adi Fitra; Susan Kustiwan; Tri Ngudi Wiyatno

Volume/Issue : Volume 9 - 2024, Issue 7 - July


Google Scholar : https://tinyurl.com/5n8nnw6b

Scribd : https://tinyurl.com/3hrb6pfe

DOI : https://doi.org/10.38124/ijisrt/IJISRT24JUL120

Note : A published paper may take 4-5 working days from the publication date to appear in PlumX Metrics, Semantic Scholar, and ResearchGate.


Abstract : Housing development projects are developing very rapidly. Housing development projects will increase people's income and standard of living. One of the housing development projects in Bekasi City is the Nava House Cluster housing complex. Nava House housing is a Cluster type housing complex. When working on a development project, project scheduling is required. In project scheduling, there are several methods that can be used, namely the CPM and PERT methods. Both methods can be used to minimize the time lag in project work. This thesis aims to determine the path formed in the network, the activities included in the critical path and the completion time contained in the critical path. The results of this research on the Nava House housing development project are: first, there are 3 routes in the network. second, the activities included in the critical path are A, B, C, D, E, G, H, I, J, L, M, N, O, P. Third, the house that has been worked on is analyzed using the CPM method, getting results The critical path is 57 days. Meanwhile, houses that are still early in construction or houses that are about to begin construction are analyzed using the PERT method, obtaining critical path results of 66 days.

Keywords : CPM, Critical Path, Network, PERT.

References :

  1. A. Aziz et al. , PROJECT MANAGEMENT (Theoretical and Practical Overview) , vol. 1. 2022. [Online]. Available: www.penerbitwidina.com
  2. A. Yuliana, "Analysis of the Implementation of Reconstruction Project Management on Jalan Kwandang Molingkapoto Prov. Gorontalo,” Radial - J. Perad. Science, Engineering and Technology. , vol. 4, no. 1, pp. 72–78, 2016.
  3. H. Prabowo and M. Anhar, "Optimizing Project Management at PT.Cipta Ekatama Nusantara Using the CPM/PERT Method in the Cendana Sawangan Regency Housing Development," Sekol. College of Economics. Indonesia. , vol. 1, no. 1, pp. 1–17, 2021, [Online]. Available: http://repository.stei.ac.id/id/ eprint/2891
  4. GP Arianie and NB Puspitasari, "PROJECT MANAGEMENT PLANNING IN INCREASING EFFICIENCY AND EFFECTIVENESS OF COMPANY RESOURCES (Case Study: Qiscus Pte Ltd)," J@ti Undip J. Tek. Ind. , vol. 12, no. 3, p. 189, 2017, doi: 10.14710/jati.12.3.189-196.
  5. I. Sudipta, "Project Management Study of Resources in Construction Project Implementation (Case Study: Construction of Villa Bali Air)," J. Ilm. Tech. Civil , vol. 17, no. 1, pp. 73–83, 2013.
  6. AC Siregar and I. Iffiginia, "Use of the critical path method (CPM) to evaluate project implementation time and costs," Tech. J. Science and Technology. , vol. 15, no. 2, p. 102, 2019, doi: 10.36055/tjst.v15i2. 6816.
  7. A. Angelin and S. Ariyanti, "Analysis of New Product Development Project Scheduling Using Pert and Cpm Methods," J. Ilm. Tech. Ind. , vol. 6, no. 1, pp. 63–70, 2019, doi: 10.24912/jitiuntar.v6i1.3025.
  8. YS Susilo, "Project Implementation Analysis Using the CPM and PERT Methods (Case Study of the University of Riau Main Stadium Implementation Project (Multi Years)).," J. Univ. Riau , p. 16, 2011.
  9. Abdurrasyid, Luqman, A. Haris, and Indrianto, "Implementation of PERT and CPM Methods in the Ship Building Project Management Information System (Implementation of PERT and CPM Methods in the Ship Building Project Management Information System)," J. Komput Science. and Inform. Khazanah Inform. , vol. 5, no. 1, pp. 28–36, 2019.
  10. MR Adyatma and TS Hadi, "Analysis of Housing Location Determination by Developers for Low-Income Communities Around Industrial Areas," J. Kaji. Space , vol. 1, no. 2, p. 198, 2022, doi: 10.30659/jkr.v1i2.20025.
  11. T. Iluk, A. Ridwan, and S. Winarto, "Application of the CPM and PERT Methods in the 3 Floor Parking Building of Grand Panglima Polim Kediri," J. Manaj. Technol. Tech. Civil , vol. 3, no. 2, p. 162, 2020, doi: 10.30737/jurmateks.v3i2.1054.
  12. U. Hasdiana, “No主観的健康感を中心とした在宅高齢者における 健康関連指標に関する共分散構造分析Title,” Anal. Biochem. , vol. 11, no. 1, pp. 1–5, 2018, [Online]. Available: http://link.springer.com/ 10.1007/978-3-319-59379-1%0Ahttp://dx.doi.org/ 10.1016/B978-0-12-420070-8.00002-7%0Ahttp: //dx.doi.org/10.1016/j.ab.2015.03.024%0Ahttps://doi.org/10.1080/07352689.2018.1441103%0Ahttp://www.chile.bmw-motorrad.cl/sync/showroom/ lam/ice/
  13. T. Alawiyah, YS Mulyani, MA Gunawan, R. Setiaji, and H. Nurdin, "Web-Based Project Management Information System (SIMAPRO) (Case Study: PT. Arya Bakti Saluyu)," J. Khatulistiwa Inform. , vol. 10, no. 2, pp. 129–135, 2022, doi: 10.31294/jki. v10i2.14061.
  14. A. Maulidi, S. Arifin, and H. Suyoso, "Construction Project Scheduling Using the Critical Path Method (Case Study: Integrated Laboratory Building, Faculty of Engineering, University of Jember)," J. Ilm. MITSU , vol. 9, no. 1, pp. 1–8, 2021, doi: 10.24929/ft.v9i1.992.
  15. RA Husna, NF Ilmiyah, and NC Resti, "Implementation of CPM and PERT in Predicting the Duration and Cost of Building Al-Ikhlas Prayer Rooms in West Kotawaringin," J. Focus Action Res. Math. (Factor M) , vol. 5, no. 1, pp. 97–109, 2022, doi: 10.30762/f_m.v5i1.633.
  16. A. Witania, A. Dana Nugraha, L. Fajar Sari, N. Lia Megawati, and N. Nur Fadillah, "Comparative Analysis of The Most Frequently Used IT Project Management Methods in Indonesia and Abroad: Literature Review," vol . 15, no. 2, pp. 299–316, 2022.
  17. AK Tama, L. Anggraini, and B. Tutuko, "Construction Management Performance Analysis on the Semarang State University Digitized Building Project," J. Tek. Civil , pp. 1–15, 2020.
  18. Christian, Cefiro, and Sentosa, "Case Study of the Application of the PERT Method in the Warehouse X Project," J. Univ. Kristen Petra , pp. 1–8, 2013, [Online]. Available: https://media.neliti.com/media/ publications/81512-ID-studi-case-penerapan-method-pert-pada-p.pdf
  19. H. Prasetya, "Application of Project Management Methods in Improving the Quality of Information Technology-Based Libraries," Ideguru J. Karya Ilm. Teacher , vol. 6, no. 3, pp. 247–256, 2021, doi: 10.51169/ideguru.v6i3.278.
  20. A. Ozaga and AA Arzi, "Project Management: Designing a Learning Management System (LMS) for Learning Information Systems Using the Critical Chain Method," August , vol. 02, no. 1, p. 1, 2022.

Housing development projects are developing very rapidly. Housing development projects will increase people's income and standard of living. One of the housing development projects in Bekasi City is the Nava House Cluster housing complex. Nava House housing is a Cluster type housing complex. When working on a development project, project scheduling is required. In project scheduling, there are several methods that can be used, namely the CPM and PERT methods. Both methods can be used to minimize the time lag in project work. This thesis aims to determine the path formed in the network, the activities included in the critical path and the completion time contained in the critical path. The results of this research on the Nava House housing development project are: first, there are 3 routes in the network. second, the activities included in the critical path are A, B, C, D, E, G, H, I, J, L, M, N, O, P. Third, the house that has been worked on is analyzed using the CPM method, getting results The critical path is 57 days. Meanwhile, houses that are still early in construction or houses that are about to begin construction are analyzed using the PERT method, obtaining critical path results of 66 days.

Keywords : CPM, Critical Path, Network, PERT.

Never miss an update from Papermashup

Get notified about the latest tutorials and downloads.

Subscribe by Email

Get alerts directly into your inbox after each post and stay updated.
Subscribe
OR

Subscribe by RSS

Add our RSS to your feedreader to get regular updates from us.
Subscribe